Route 9 / Route 287 Roundabout

Overview

  • The project consists of approximately one mile of roadway improvements, including a two-lane roundabout at the intersection of Route 9 and Route 287. 
  • Improvements will also include new drainage and stormwater facilities as well as relocation of some utilities. 
  • When complete, the project will significantly reduce existing traffic congestion, improve safety and provide a long-term, cost-effective solution for future maintenance.  
  • The Virginia Department of Conservation and Recreation, Virginia Department of Game and Inland Fisheries, and the US Fish and Wildlife Service determined that the project should have no impact on threatened or endangered species.

Current Phase: Right of Way Acquisition

Estimated Timeline

  • Fall 2021 - Fall 2022: Right of Way Acquisition
  • Winter 2023 - Fall 2023: Utilities Relocation 
  • Winter 2024 - Spring 2024: Procurement of Construction Contractor
  • Spring 2024: Award Contract – Construction
  • Spring 2024: Notice to Proceed – Construction
  • Spring 2024 - Spring 2026: Construction
  • Spring 2026: Substantial Completion