Lucketts Fire and Rescue Station Replacement

Project Overview

  • This project will construct a new 18,000 square foot Fire and Rescue facility on 14.36 acres to replace the existing Lucketts Volunteer Fire and Rescue Station.
  • The station will consist of four pull through apparatus bays, seven 2 person bunk rooms, a training room, restrooms, showers, kitchen and dining areas, supply storage, a gear and hose drying area, fitness room, offices and a repair shop.
  • The facility is designed to achieve LEED Gold designation.
  • Funding for land acquisition for the fire station replacement was provided in FY 2013 in the Land Acquisition Fund.
  • The project is estimated for completion in the winter of 2021.

Current Status:  April 2020

  • Crews will complete structural concrete masonry unit block walls and structural steel by the end of this month. 
  • Work on site grading, storm water ponds and erecting supporting structures will continue as weather permits. 
  • Electrical work has begun, including the rough installation of the electrical wiring, boxes, fixture mounts and breaker panels. 
  • Work to pour the concrete slab and install exterior systems that protect the structure from the weather is currently scheduled to begin in May 2020.

Construction Progress Photos