Lovettsville Community Center

Overview

  • This project will design and construct a new community center building in the Town of Lovettsville, replacing the existing building.
  • The new Community Center will be over 15,000 square feet and will have a full-size gymnasium, five classrooms, a multipurpose room, kitchen, administrative offices, meeting space and storage areas.  
  • The project also includes a 600-square-foot addition and renovation to the existing 1,200-square-foot Pool House.
A drawing of the proposed new Lovettsville Community Center. It is a brown, one-story building with

Current Status: June 2020

  • Work initiated at the end of March to finish the geothermal wells and parking lot has been completed.
  • Phase 1 of the original construction schedule is now complete, including the sediment basin, riser structure, pond access road, fencing, and the temporary access road connecting East Broad Way to the gravel parking lot.
  • Due to the termination of the construction contract in January 2020, the remaining phases of construction of the new community center are delayed until a contractor can be procured. Preparations for the contractor bidding process are underway.
  • Construction is estimated to resume in late 2020.