Current Status: April 2022
- Storm water infrastructure installation is complete.
- Curb and gutter installation between the WO&D Trail Bridge and the Tuscarora Creek Bridge is complete.
- Crews have completed work on the bridge approaches for the bridges over Tuscarora Creek and the W&OD Trail, connecting the bridge decks to the adjacent roadway.
- For the next several weeks, crews will begin final grading at trails in preparation for pouring asphalt.
- Ongoing work includes fine grading to prepare for seeding in unpaved areas as weather allows.