Crosstrail Boulevard: Kincaid to Russell Branch

Overview

  • This project funds the construction of a new four-lane, median divided road segment, extending Crosstrail Boulevard from Kincaid Boulevard to Russell Branch Parkway at its existing intersection with River Creek Parkway. The project includes the following major elements:
    • 115 ft. long bridge that will carry Crosstrail Boulevard over the W&OD Trail Regional Park.
    • Direct pedestrian or bicycle connection between the W&OD Trail and Crosstrail Boulevard. 
    • 500 ft. long bridge that will carry Crosstrail Boulevard over Tuscarora Creek.
    • Five storm water retention facilities. 
  • When completed, Crosstrail Boulevard will provide a new connection in southeastern Leesburg between Sycolin Road near Philip A. Bolen Memorial Park and Route 7.
  • In a future project, Crosstrail Boulevard will be extended beyond Sycolin Road to link to the Dulles Greenway interchange at Shreve Mill Road. The county is scheduled to begin design and development later this year; construction will not begin prior to 2024.


Construction Progress Photos

Current Status: April 2022

  • Storm water infrastructure installation is complete.
  • Curb and gutter installation between the WO&D Trail Bridge and the Tuscarora Creek Bridge is complete. 
  • Crews have completed work on the bridge approaches for the bridges over Tuscarora Creek and the W&OD Trail, connecting the bridge decks to the adjacent roadway. 
  • For the next several weeks, crews will begin final grading at trails in preparation for pouring asphalt.
  • Ongoing work includes fine grading to prepare for seeding in unpaved areas as weather allows. 