Belmont Ridge Road Improvements

Overview

  • This project funds the design, land acquisition and construction of the reconstruction and widening of Belmont Ridge Road between Truro Parish Drive and Croson Lane from an existing two lane rural road to a four lane median divided suburban roadway with shared use paths on each side.
  • The road plans were approved by the Virginia Department of Transportation and the Loudoun County Department of Building and Development (B&D) in June 2017. In November 2019 acquisition of land rights for the project was completed. 
  • The project funding comes from a variety of funding sources including local tax funding, General Obligation Bonds, and the Northern Virginia Transit Authority (NVTA).

Current Status: September 2020

  • Utility relocation is underway.
  • Utility relocation will take place from fall 2020 to spring 2022.
  • Construction is estimated to begin in spring 2022 and to be completed in winter 2025.  

Stay Informed About This Project

Related Documents

Contact Us

If you have questions about this project, email county staff or call 703-737-8624.

Media Inquires

Email Glen Barbour, Public Information Officer or call 703-771-5086.