Moorefield Station Community Park

Overview

  • This project develops an 84-acre community park co-located on the same site as the Moorefield Station Elementary School.
    • This project will provide two rectangular fields and one diamond field with field lighting, trail and sidewalk network, restrooms, concessions and parking adjacent to the school. 

Current Status: August  2020

  • Light level testing on the two soccer fields will take place on August 5, 2020. Musco Lighting will start the tests at dusk, allowing one hour for each of the two large soccer fields to be tested. Tests are expected to be completed by midnight. If inclement weather postpones testing, testing will begin on the next day. 
  • Light level testing was completed on July 13, 2020, on one baseball field and perimeter property lines. 
  • The construction contract was awarded to Meridian Construction on May 30, 2019. 
  • Notice to Proceed with construction was issued on July 9, 2019.
  • This project, weather permitting, is scheduled to be completed in the fall 2020.