The Potomac Green Park project includes construction of a 28-acre park in Ashburn, VA. This park was dedicated to the County by the developer and will contain three multi-purpose athletic fields for soccer, football and lacrosse, and one baseball field. The park will also include an ADA accessible restroom facility, concession stand, sidewalks and trails, pavilions, bleachers, playground, off-leash area, tennis/pickle ball court, and a bocce ball court. 

Current Status: August 2020

  • The county’s contractor, Waynesboro Construction, received notice to proceed on August 13. 
  • Construction mobilization is underway, including establishing construction trailers and installing perimeter fencing.
  • Next month, installation of erosion and sediment control measures will begin in preparation for the start of site demolition and mass earthwork.