This project provides for the installation of a traffic signal and turn lanes at the intersection of Braddock Road (Route 620) and Supreme Drive (Route 1257) and Summerall Drive (Route 1258). In addition, the two lane section of Braddock Road near the intersection will be widened to four lanes.

Current Phase: Award Contract - Construction

Estimated Timeline

  • Spring 2023: Notice to Proceed – Construction
  • Spring 2023 - Summer 2024: Construction
  • Summer 2024: Substantial Completion