Sterling Park Safety Center

Overview

  • This project provides funding to design and construct a new 22,000 square foot replacement station for the Sterling Volunteer Fire and Rescue Companies at the corner of East Holly Avenue and Commerce Street in Sterling. 
  • The new station will replace the current 8,772-square-foot building on this site dating from 1970, and provide more storage and parking. The one-acre property will also expand by a third of an acre. 
  • Features of the facility will include a reception area, meeting and training rooms, bunk rooms, a kitchen, an exercise room, offices, apparatus bays, and storage space for equipment and gear. 
  • Funding for this project uses general obligation bonds and cash proffers.

Current Phase: Construction

Estimated Timeline:

  • Winter 2021-Spring 2023: Construction
  • Spring 2023: Substantial Completion