Prentice Drive - Loudoun County Parkway to Shellhorn and Lockridge West

Overview

  • This project provides for the planning, design, right of way (ROW) acquisition and construction of Prentice Drive (Route 1071) from Loudoun County Parkway (Route 607) to Shellhorn Road (Route 643) at its intersection with Metro Center Drive and a new road, Lockridge West, between Prentice Drive and Waxpool Road.
  • The project was recommended as an essential road connection to provide connectivity to the planned Ashburn Metrorail Station identified in the 2010 Countywide Transportation Plan (CTP). Both roadways will be designed as four-lane urban major collectors, with associated turn lanes and bicycle/pedestrian lanes.
  • Funding for the project includes Local Tax funding, cash proffers and regional funding from the Northern Virginia Transportation Authority (NVTA).
  • This project is funded using local tax funding, NVTA 30% local funds, and NVTA 70% regional funds. Design completion is currently estimated for 2023. 

Current Phase: Design - 100% Design Plans

Estimated Timeline

  • Winter 2020 - Fall 2022: Design
  • Winter 2023 - Fall 2023: Land Acquisition
  • Winter 2023 - Fall 2023: Right of Way Acquisition
  • Winter 2024 - Summer 2024: Utilities Relocation 
  • Summer 2024 - Fall 2024: Procurement of Construction Contractor
  • Winter 2025: Award Contract – Construction
  • Winter 2025: Notice to Proceed – Construction
  • Winter 2025 - Fall 2026: Construction
  • Fall 2026: Substantial Completion