Crosstrail Boulevard - Sycolin Road to the Dulles Greenway

Overview

Crosstrail Boulevard from Sycolin Road to the Dulles Greenway (Segment C) project provides for the design, right of way acquisition, utility relocation and the construction of a four-lane median-divided road between Sycolin Road and the Dulles Greenway Interchange. The length of this project is approximately 2,700 linear feet and it includes four-span bridge over the south tributary to Sycolin Creek.

  • Funding for this project is from the Northern Virginia Transportation Authority (NVTA) and local funds.
  • The Commonwealth Transportation Board approved Limited Access Control Change on September 21, 2022. 

Current Phase: Design - 100% Design Plans

Estimated Timeline

  • Winter 2021 - Fall 2022: Design
  • Winter 2023 - Fall 2023: Right of Way
  • Winter 2024 - Spring 2024: Utilities Relocation 
  • Summer 2024 - Fall 2024: Procurement of Construction Contractor
  • Winter 2025: Award Contract – Construction
  • Winter 2025: Notice to Proceed – Construction
  • Winter 2025 - Spring 2026: Construction
  • Spring 2026: Substantial Completion