  • This project provides for the planning, design, right-of-way acquisition, and construction of the realignment of Evergreen Mills Road at the intersections of Reservoir Road and Watson Road. 
  • The improvements propose a new four-way signalized intersection between Evergreen Mills Road, Watson Road and Reservoir Road. 
  • This project is an existing Capital Improvement Program (CIP) project that was also identified as a long-term recommendation in the Evergreen Mills Road Safety Audit and Improvements completed in 2019. 
  • The project is designed to improve lines of sight and safety along this segment of Evergreen Mills Road, while adding right and left turn lanes from Evergreen Mills onto Watson Road and Reservoir Road.
  • A virtual public information meeting was held in September 2020 and design endorsement from the Board of Supervisors was received in February 2021.

Current Status: July 2022

  • The design team is working to address comments received from the County's Department of Business and Development (B&D) and Virginia Department of Transportation (VDOT) on 90% design plans submitted for review in February. Development of 100% plans is underway with anticipated review submission to stakeholders estimated for August 2022. 
  • Land acquisition efforts are currently anticipated to begin in late 2022.

Stay Informed About This Project

Related Documents

Contact Us

If you have questions about this project, email county staff or call 703-737-8624.

Media Inquiries

Email Glen Barbour, Public Information Officer or call 703-771-5086.

Meeting Documents