Once all of the work is complete, you can request release of the bond.  No bond shall be released from a Performance Agreement that is in default.

If your project contains privately maintained roads or storm water ponds, you must provide a Latent Defect and Indemnification Agreement and Bond.

Release of cash bonds may take up to four weeks once the release is authorized by the Director of the Department of Building and Development.


 

Condition

Agreement

LDIA Streets


Your project is completed and your project contains privately maintained roads

LDIA Agreement Form - Private Streets

LDIA Ponds

Your project is completed and your project contains storm water ponds

LDIA Agreement Form - Bonded Pond 

Proffer Cert

Your project is complete and is subject to proffers or conditions of approval.

Loudoun County Proffer Condition Certificate